Assessment of Resource Management by Using Primavera Software
 
Mr. Pritam Pradip Rokade1* Prof. N. N. Morey2 Prof. U. J. Phatak3
1 PG Student (Construction Management) Department of Civil Engineering, PVPIT Bavdhan (Kh), India)
2,3 Assistant Professor, Dept. of Civil Engineering PVPIT Bavdhan (Kh) India)
Abstract – Resource planning and management assists in the future and the use of the board using PRIMAVERA provides greater control, monitoring and a clear calendar of purpose. Asset Management minimizes business losses that may result in the largest types of asset operations. The asset board is a major problem that needs to be addressed in order to maintain the artistic distance from the delay of the promise. The Asset Board enables the organization to use the most available assets. The idea behind asset management is to reduce the cost of disposal of assets in construction for example standing below the share of assets. According to the actual management agreement, the penalty is fixed when the work ends after its due date. A few jobs pass a higher fine than others. At this business center it can make the transition between job pay and can create a time-consuming and time-consuming process for managers to distribute assets, fulfilling client skills. A business manager consistently and consistently wishes to fulfill the interests of his or her partners in terms of cost, quality and time.
Keywords - Resource Management, Primavera Software, Construction.
1. INTRODUCTION
The Resource Schedule gives an idea of ​​which resource is assigned to which function. Provides information for each category (for example, all employees, or all equipment) and indicates which of the information you are assigned to perform in a timeline that can be displayed on an hourly, daily, weekly or monthly basis. The objects for each task such as tasks are called Events in Visual Planning and are displayed as color blocks in the program. Monitoring and control can be well done in the system if multiple types of resources users can easily switch from one schedule view to another or show multiple schedules simultaneously in one frame. This is called Multi-Purpose Planning.
The software used for the primavera application of Project management strategies can be used to solve resources and is also useful in reducing project time and costs within the limited availability of resources that work to make the project profitable and save time. Research on the effectiveness of a resource building project schedule using primavera.
1.1 Scope of project
Resource planning and management assists in the future and the implementation of project management using PRIMAVERA provides good control, monitoring and a clear project plan. Resource management minimizes project losses that can be caused due to significant variability in resource utilization. Service management is a major problem that needs to be addressed to avoid project delays. Resource management helps the organization to make use of available resources up to that point .The idea behind resource management is to reduce resource depletion to work i.e. to stop allocating resources. In the case of a real project management environment, a fine is imposed if the project is completed after its due date. Some projects carry higher fines than others. In this project manager it can facilitate trade between project fees and can highlight an effective cost and time management system for well-allocated resources, which satisfies customer needs. The project manager is always under pressure to satisfy the needs of his / her stakeholders in terms of cost, quality, time and scope.
1.2 Objectives of Report:
To read the terms of service management and primavera software.
Evaluate the input requirements for the distribution of primavera software
Create a limited reckoner sheet to reduce resource allocation problem
Comparing the standard planning process with primavera over time and cost
1.3 Overview of resource planning
As a result of the above work relating to all property in relation to the use of primavera. The estate plan gives an idea of ​​who the assets are entrusted to. Provides details of the different assets of a category (for example, all representatives, or all equipment) and indicates which of these assets are assigned to perform in a period that is not shown on an hourly, daily, weekly and weekly or monthly scale. A variety of work items, for example, travel are called time in visual planning and emerge as scenes of fast barking. Care and control should be best applied to bookings where multiple types of assets are used by clients without many changes starting with one asset plan look and move on to the next or show a few strategies quickly in one framework. This is called multi-asset planning. The primavera system used for Project work plans can be used to look at assets and continue to help reduce work lengths and costs within the limited access to assets to make the work more profitable and overtime. Focus mainly on improving the duration of compulsory labor using primavera.
2. CASE STUDY
Fig 1 3rd Eye view of actual site
2.1 PROJECT ATTRIBUTES
Project features reflect the details of an ongoing project depending on the project plan, the strength required for the various tasks to perform a critical resource analysis. The costs incurred in the project are also disclosed.
2.2 PROJECT DETAILS
Name of the project : 18LAttitude Construction of Commercial Building Built up area : 92000 sq.ft.
Number of Storey’s : Ground + Six Floors Floor to Floor height: 3.35m
Height of Plinth: 0.50 m above Ground Level Depth of Foundation: 1.50 m below Ground Level. External Walls: 250 mm thick including plaster Internal Walls: 150 mm thick including plaster Parapet Walls : 250 mm thick including plaster
2.3 APPLYING RESOURCE MANAGEMENT BY RESOURCE LEVELING
1. STEP NO-1 CALENDER
Fig 2 Creating Calendar
STEPNO-2 OBS
Fig 3 Creating Organizational Breakdown Structure
STEPNO-3 WBS
Fig 4 Creating Work Breakdown Structure
Fig 5 Add Resources
STEP NO-5 ACTIVITY CREATE
Fig 6 Crating Activities
STEP N0-6ASSIGN RESOURCESS IN PRIMAVERA
Fig 7 Assign Resources
Fig 8 Resources and No of Resources
The investigation was completed in two phases. For the most part, all the details and information expected to measure assets are collected. The development period using tested assets was suspended as a Gantt diagram and the necessary assets for the entire organization are planned. The pinnacle units required for a step-by-step party are from Resource histograms. In the second phase, the actual assets available to the company have been categorized by Resource leveling with an extended term. Time-cost cost proposals discuss management awareness Leveler tool allows you to plan exercises in a way that minimizes or kills excess baggage stocks with more than one movement within the road or by cutting through multiple tasks. Uninstalled administrators require integrated resources and integrated stacks to enable effective recognition and attainment of their work objectives
3. CONCLUSION
1. With the rise of world construction, the work of the construction process as it rises dramatically is miraculous. Effective resource management therefore minimizes time loss. Continue research appropriate resource management research provides project clarity.
2. The type of construction sector differs from the type of complex access to resources that results in risk and natural validation at all stages of the life cycle of the project. In fact, facial resource management is essential for a construction project to be successful in achieving its project objectives. Active resource allocation is required on the construction site to complete the project within the stipulated time. Resource evaluation is required in construction projects to avoid difficulties associated with significant variability in resource performance.
3. Resource utilization and resource planning problem is one of the most important issues in project implementation and has been addressed by the project manager.
4. In today's developing nation, it is necessary to develop our knowledge in order to learn various resource management techniques. This assignment and various skilled workers can be advanced with Primavera software.
5. More skilled workers should be selected first and used as working time workers to achieve the best results. Due to efficiency and resource planning, time and cost should be well managed.
6. The main purpose of this study was to understand the role of monitoring and control in the continuous and timely completion of construction work. This objective is achieved through a review of the literature and methods involved in monitoring and management.
7. In order to properly plan the planning and management of a construction project it is very important to use a software management program. This study demonstrates the importance of resource management in a major construction project. This is because effective resource management by Primima P6 construction development costs sometimes increase due to the loss of control system controlled by time delays and reduced. Case studies have been a guide to understanding the progress of a residential and commercial construction project. Companies that do not use primavera software tools effectively should increase their investment in training and mentoring their recruited teams.
REFERENCES
  1. Deeptisahu, A. K. Jain (2007). ‘Resource planning of a colony project primavera’, Vol. 6 using, Issue.
  2. S.K. Nagarjun and B. Shivakonda Reddy (2012). Resource management in construction project’, vol. 2, Issue.
  3. A. Kastor, K. Sirakolis (2008). ‘The effectiveness of Resource leveling tools for resource constraint project scheduling problem ’, Issue.
  4. Hamed Zaidostan , mohammad Mahigholipoor (2013) ‘using primavera software in resource allocation and project of construction project’, Vol. 4, Issue.
  5. S. K. Nagaraju, B. Sivakonda Reddy (2014). ‘Resource Management in Construction Projects – a case study’. Vol. 4, Issue.
  6. Hong-Hai Tran, Nhat Hoang (2014). ‘Anovel Resource leveling approach for construction projectbased on different evalution’.
  7. Hitanshu Saini, Khushpreet Singh, Uma Malik (2017). Project management in construction using primavera’ issue.
  8. Akshay R. Kohli (2017) enterprise project management using primavera’ vol 4 ,issue 2017
  9. Vijya Bhosale, Prof. Dr. S. S. Shastri (2017). A review of genetic algorithm used for optimizing scheduling of resource constraint construction projects
  10. Nikhil R. Mahajan, Vaishali Joshi (2017). ‘Resource scheduling in construction project using MSP’ Vol. 6, Issue.
  11. Piyush Pramod Bagade and Prof Abhijit Bhirud (2018). Review construction project management software primavera’ Vol. 4.
  12. Suvarana, Yateen Lokesh, Dr. S. P. Mahendra (2017). ‘Planning, Scheduling and tracking of ongoing bridge constructon project using Primavera software’ issue 2017
  13. Atilla Damci (2013). Multiresource leveling in line of balance scheduling’ Vol. 139, Issue.
  14. Aftab Hameed Memom, Rosil Mohammad Zin (2010). ‘Resource driven scheduling implementation in Malaysian construction industry’ Vol. 1, Issue.
  15. Satinder Chopra, Arvind Dewangan (2014). Developing an Efficient Schedule in Primavera P6: Significance of Activity ID & Descriptions, International Journal of Innovative Research in Science, Engineering and Technology (An ISO 3297: 2007 Certified Organization) Vol. 3, Issue 7.
  16. V.dhanalakshmi (2016) High cost infrastructure report monitoring by p6 software, international conference on engineering innovations and solutions (ICEIS – 2016)
  17. P. Esakki Thangam, R. Magdalene Benila (2016) Planning, Scheduling and Time Management of Six Lanes Road Construction Work at V.O.C Port Trust using Primavera P6 Software IJSTE - International Journal of Science Technology & Engineering | Volume 2 | Issue 11 | May 2016
  18. Unmesh. Y. Polekar, Rohit. R. Salgude (2015). Planning, Scheduling and Tracking of a residential Project using Primavera Software, International Journal of Advance Research in Computer Science and Management Studies, Volume 3, Issue 5, May 2015
  19. T. Subramani, A. Sarkunam, J. Jayalakshmi (2014). Planning and Scheduling of High Rise Building Using Primavera, T. Subramani et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6 (Version 5), June 2014, pp. 134-144
  20. Vishal Annappa Nimbal, Prof. Balasaheb Jamadar (2017). Planning, Scheduling and Allocation of Resources for multi-storied Structure using Oracle’s Primavera p6 software, International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 |